Quick answer: In a process with the State, the bond is not a piece of paper you upload and forget. It has to match the tender specifications in value, validity period, and coverage, and the entity must approve it within SECOP II. The most common thing I see is that the bidder meets the minimum percentage required by law, but the specifications called for more, or the file is uploaded and nobody approves it. Result: contract signed, but unable to start.

Before thinking about guarantees, make sure you are qualified to bid. If your registry is not up to date yet, start with how to register or renew the RUP at the Chamber of Commerce, and also review the general RUP guide. This guide is informational: it does not replace the tender specifications, the issued bond, or advice from a lawyer, and it does not guarantee award.

What a guarantee is and which forms you can use

A guarantee in public procurement is the backing the entity requires to protect itself if the bidder or contractor defaults. According to article 2.2.1.2.3.1.2 of Decree 1082 of 2015, there are three types: insurance contract contained in a bond, autonomous patrimony, and bank guarantee.

In practice almost everyone uses an insurance bond, but it is not the only option. One important exception: extracontractual civil liability can only be covered by an insurance contract (article 2.2.1.2.3.1.5). Autonomous patrimony and bank guarantees do not work there.

Bid bond (garantía de seriedad de la oferta)

It is submitted together with the bid and has a sanctioning nature: if it is enforced, the entity receives the insured amount without having to prove the amount of damages. According to article 2.2.1.2.3.1.9, the value must be at least 10% of the bid value, and its validity runs from the submission of the bid until approval of the performance guarantee.

It covers events such as not signing the contract without just cause, withdrawing the bid after the deadline, not providing the performance guarantee, and not extending validity when award or signing is extended. The details of that last event and of the extension periods are in article 2.2.1.2.3.1.6 and in your tender specifications; read them there instead of relying on summaries.

Watch out for two things. First: the specifications may require more coverage or longer validity than the legal minimum. Second: Decree 1860 of 2021 allows Colombia Compra Eficiente to define a differential sufficiency for startups, women-owned companies, and Mipymes. This guide does not set that percentage; verify the current figure at colombiacompra.gov.co.

Single performance guarantee and its coverages

Once the contract is awarded, the single performance guarantee is established, which can combine several coverages. The main ones:

  • Performance: minimum validity until the contract is liquidated and value of at least 10% of the contract value (article 2.2.1.2.3.1.12). If the contract exceeds one million SMMLV, the floor may go down and is calculated on the contract value. Between more than one million and five million SMMLV, the entity may accept at least 2.5%. Between more than five million and ten million SMMLV, the floor may be at least 1%. Above ten million SMMLV, it may accept at least 0.5%. That scale is calculated on the contract, not on the bid, and does not apply to bid bonds.
  • Advance or advance payment: if one exists, the coverage is 100% of that sum, in money or in kind.
  • Wages, social benefits, and labor compensation: value not less than 5% of the total contract value and validity for the contract term plus three years, counted from the agreed end date (article 2.2.1.2.3.1.13).
  • Stability and quality of the work: the value is set by the entity; the validity is not less than five years from receipt to the entity's satisfaction (article 2.2.1.2.3.1.14).

The quality of services and the quality of goods are also covered, but their value and validity are set by the entity in the process documents. There is no universal number you can copy.

What the wages coverage does not do

This is the most costly misunderstanding. The coverage protects the entity against damages it suffers from the contractor's labor non-compliance. It does not by itself pay your workers' payroll: if they do not claim from the administration and the administration has not acknowledged the debt, there is no automatic payment. It mainly applies to contracts with personnel, such as construction, cleaning, or security.

Work stability: neither always five years nor less than one

Following Decree 399 of 2021, the entity may set a term shorter than five years when technically justified, but never less than one year. And it is counted from receipt to the entity's satisfaction, not from signing.

Detalle de escritorio con hoja en blanco, almohadilla de sello y portátil cerrado

When the entity may not require guarantees

They are not mandatory in direct contracting, minimum-amount procurement, or purchases in large retail stores (article 2.2.1.2.1.4.5). The decision must be justified in the preliminary studies and documents, as also set out in article 2.2.1.2.1.5.4. In the other procurement modalities, bid and performance guarantees are treated as mandatory.

My advice: do not assume. If the invitation or specifications require a bond, provide it exactly as that document says, even though the law would allow you to omit it.

How it is uploaded and approved in SECOP II

The order matters. Once the contract is already approved and published, the provider sends the file link to whoever issues the guarantee; it is processed and submitted through SECOP II. The entity reviews it under Contracts, contract detail, Configuration, guarantees. If it has an approval workflow, it uses "Send for approval" and only then can publish it; if it rejects it, it must justify the decision.

Approval is an act within the platform. According to opinion C-1582 of 2025 from the Relatoría of Colombia Compra, an external letter or PDF does not replace it, and a professional services contractor has no authority to approve bonds. So be careful with anyone who offers to "get the bond approved" in exchange for payment or with a PDF record: that does not substitute the entity's approval in SECOP II.

If you are self-employed and will invoice after starting work, also review the guide to invoices (cuenta de cobro) and supporting documents. It is a separate procedure: an invoice is not a guarantee.

Checklist before submitting the bond

  1. The beneficiary is the contracting entity, with its correct NIT.
  2. The process or contract number and subject match those in the specifications.
  3. The insured value of each coverage was calculated on the correct base: bid for bid bond, contract for performance.
  4. The start and end dates of each coverage cover the required validity (liquidation, term plus three years, five years from receipt).
  5. The percentages in the specifications, if they exceed the legal minimum, are reflected.
  6. If there is an advance, its 100% coverage exists.
  7. The policyholder's name or corporate name matches your bid and your RUP.

This time cost is real: a date correction can send the bond back and delay the start. This guide cannot set how much an insurer charges; that amount depends on your case and you must request it directly.

Dated note: Monday, October 12, 2026

That day is reported as a national holiday and, falling on a Monday, is not moved. That does not by itself suspend the deadlines in the specifications or the insurers' business hours. If your deadline or approval is close, confirm your insurer's cutoff in advance. The Colombia Compra service desk, according to its consulted page, operates Monday to Friday from 7:00 a.m. to 7:00 p.m. and Saturdays from 8:00 a.m. to 12:00 p.m. (verify the current figures at the official source).

Practical close: read the specifications twice, compare each line with the issued bond, and do not consider anything approved until you see it approved in SECOP II.

Frequently asked questions

❓ Is the bid bond always 10% of the bid?

The legal floor is at least 10% of the bid value, but the specifications may require more. Do not apply the 2.5%, 1%, and 0.5% scale, which corresponds to performance for very large contracts. There is a differential sufficiency for certain bidders (verify at the official source).

❓ Until when must the performance guarantee be in force, and on what value?

At minimum until the contract is liquidated, and for at least 10% of the contract value, not the bid value. The lower scale applies only if the contract exceeds 1,000,000 SMMLV, according to article 2.2.1.2.3.1.12. Also check what your specifications require (verify at the official source).

❓ Does the wages coverage pay the workers?

Not directly. It covers damages the entity suffers from the contractor's labor non-compliance, and it does not pay payroll if the workers do not claim from the administration and the administration does not acknowledge the debt. The minimum is 5% of the total value and the validity is the contract term plus three years (verify at the official source).

❓ Is work stability five years counted from signing?

No, it is counted from receipt of the work to the entity's satisfaction, and it must not be less than five years unless justified. Following Decree 399 of 2021, the entity may set a shorter term, but never less than one year. The value is set by the entity (verify at the official source).

❓ Is it enough to upload a PDF or a signed record in SECOP II?

No. The entity must approve the guarantee within the platform, and an external PDF or letter does not replace that step. Also, a service contractor cannot approve bonds. If someone charges you to "get it approved," be wary (verify at the official source).

❓ In minimum-amount or direct contracting, do they always require a bond?

Not always. In direct contracting, minimum-amount procurement, and purchases in large retail stores, the guarantee is not mandatory, but the entity must justify in the preliminary studies whether it requires one. If the invitation requests it, you must provide it as specified (verify at the official source).

❓ Can I replace the bond with a bank guarantee or autonomous patrimony?

Yes, for bid and performance, because the law admits insurance bonds, autonomous patrimony, and bank guarantees. The exception is extracontractual civil liability, which can only be covered by an insurance contract. Confirm what your specifications accept (verify at the official source).

Get practical Colombia guides & local listings

No spam. Housing, jobs, vehicles, and everyday Colombia guides delivered weekly.

Comments

Loading comments...

Checking sign-in status...

Keep reading

More useful guides around this topic.

All guides